Exercise 6: Work Content Times

Lesson
Materials

Now that we have built Effective Work Minutes into our Resource Calculation spreadsheet, and calculated Takt Time for each process, we will incorporate data on Standard Times, by process, for both labor and machine-driven activities.  These Standard Times will have been developed by pTool’s manufacturing engineering (ME) team, or by knowledgeable persons working in each production area.  In cases where formal Standard Times have not been developed, we recommend using published industrial engineering standards as a consistent and reliable substitute for Line Design purposes.