2.5 List Production Resources [STREAM*]

Create a detailed list of all production machinery, equipment, other fixed assets, and people in the target areas. If there are specialty labor categories in the target processes, document them too. You don’t need to include hand tools in this analysis, but do include any item that would require a capital request in order to buy it. Document your results in the Line Design Workbook in the tab labeled Resource List.

This list will be important because it will be necessary to calculate resources for each of them independently. You will also need to document work time for each resource independently.

OKRs
Objective: Document all equipment and machinery to be used in the new design.
Key Result: Capture information to be used in the upcoming Resource Calculations, and initiate capital requisitions if needed.